Case No. 24-0625
Culberson Midstream was a West Texas gas gathering company whose value depended on oil and gas production from more than 43,000 Culberson County acres operated by its customer, Charger Shale Oil. Energy Transfer signed an Option Agreement to buy Culberson at floor and ceiling prices, with a put price of about $93 million that the sellers could trigger. In March 2022, six days after the sellers triggered Energy Transfer's obligation to buy, Energy Transfer and a subsidiary claimed Culberson breached, and the sellers sued.1
The trial court denied the sellers' motion for summary judgment on Energy Transfer's fraud claim and identified controlling questions of law for permissive appeal; the Dallas Court of Appeals denied the petition for permissive appeal. The sellers petitioned this Court August 5, 2024. On February 14, 2025, on a joint motion, the Court granted the petition under Rule of Appellate Procedure 56.3 and, without considering the merits, vacated the court of appeals' judgment and remanded to the trial court under the settlement agreement.
Petition for review of a court of appeals' order denying a petition for permissive appeal, under Civil Practice and Remedies Code § 51.014(h); granted and judgment vacated and remanded on a joint motion under settlement, Rule of Appellate Procedure 56.3.1
The petition asked whether a disclaimer of reliance in a letter of intent is effective against pre-contractual representations or was superseded by a merger clause in a separate contract, and whether pre-contractual warnings from the buyer's head geologist and its choice of a contract without a minimum drilling commitment are "red flags" that negate justifiable reliance as a matter of law.1 The Court did not reach them.
Culberson Midstream and the sellers (Petitioners): the questions are controlling questions of law, and answering them in their favor would end the litigation.1 Energy Transfer contended the disclaimer was superseded by a merger clause.2
The order rests on the parties' settlement; the Court did not consider the petition's reasons for review (February 14, 2025 orders).
None noted
The following is current as of October 9, 2026.
| Date | Event |
|---|---|
| 08/05/2024 | Petition for Review (Culberson Midstream Equity, LLC, et al) |
| 10/14/2024 | Response to Petition (Energy Transfer LP) |
| 10/16/2024 | Reply to Response to Petition filed (Culberson Midstream Equity, LLC, et al) |
| 02/24/2025 | Mandate issued |
Review SCOTX decisions faster than ever.
With a SCOTX Report account, receive AI-generated summaries of every opinion and order, plus direct links to the briefing, opinions, and orders themselves—so you can quickly determine whether each opinion and order deserves your attention.
Create a Free Account Log In